On 2 April 2020, the Governor of West Pomerania province issued the decision to grant construction permit for the onshore gas pipeline section from the First Dry Weld to Niechorze-Pogorzelica Line Valve station.
Thereby, GAZ-SYSTEM holds the complete set of decisions for the pipeline connecting the offshore gas pipeline to the National Transmission System.
Baltic Pipe is a strategic project design to bring Norwegian gas to the Danish and Polish markets and end users in neighbouring countries. Investing parties are the Polish Gaz-System and the Danish TSO Energinet.
The pipeline is planned to be operational by Q3 2022. It will deliver 10 billion m3 gas to Poland and Central Europe.